Koeberg mills are only but one more Eskom rip-off – Chris Yelland

Reclaws International > Uncategorized  > Koeberg mills are only but one more Eskom rip-off – Chris Yelland

Koeberg mills are only but one more Eskom rip-off – Chris Yelland

Koeberg mills are only but one more Eskom rip-off – Chris Yelland

Eskom has been in the spotlight, over all over again, as the Zondo Rate persisted its teach seize inquiry into its board and the dismissal of three senior contributors. A number of whistle blowers contain stepped ahead to shine a light-weight on circumstances of corruption. Genuinely, historical Eskom head of ethical and compliance Suzanne Daniels said cushy manipulation to award contracts to other folks pleasant to ANC contributors became the norm, and orders from the ministry of public enterprises on how Eskom change desires to be conducted took region on a day-to-day basis. Energy educated Chris Yelland delves into the unlit waters surrounding the Koeberg nuclear energy space, and the contract awarded to French contractor, Areva, below fishy terms. – Claire Badenhorst

Steam mills for Koeberg: the most costly transport of scrap metal in the historical past of humankind

By Chris Yelland*

The provision of the main of six original steam mills by Areva closing week to elongate the lifetime of Eskom’s Koeberg nuclear energy space finds but but one more rip-off at Eskom, perpetrated for the length of the rotten leadership of Brian Molefe, Matshela Koko and the dodgy Eskom board on the time.

Chris Yelland

On the premise of a three-month shorter supply time, the R5bn steam generator substitute contract became finally awarded to French teach-owned nuclear contractor, Areva, who after working into monetary difficulties, are now managed by French national electricity utility, Electricite dé France (EDF).

This followed an prolonged High Courtroom, Charm Courtroom and Constitutional Courtroom battle in South Africa, by which Westinghouse (finally unsuccessfully) tried to issue the irregular contract award to Areva on the premise that the claimed urgency of the life-extension became deliberately contrived by Eskom in portray to wrongfully award the contract to Areva.

On the time when Koeberg became constructed between 1976 and 1985, Framatome (the predecessor to Areva) manufactured the 2 900 MW nuclear reactors and the six related steam mills at Koeberg, utilizing designs licenced from Westinghouse.

Both Eskom and Areva claimed that it became fully serious for safe operation of the energy plant and for security of electricity present in South Africa that the steam mills desires to be finally modified for the length of the so-known as “X23” outage at Koeberg in 2018.

Learn also:  Chris Yelland: More finger-pointing at Eskom – COO cleared of charges

This became cited by Eskom as the reason on the support of awarding the contract to Areva, where an allegedly contrived three-month “waft” in Areva’s mission belief became indicated as the deciding component. This no matter Westinghouse having met the full technical and commercial requirements, with a lower contract mark, and a guarantee to meet the 2018 completion date on agonize of remarkable penalties.

Nonetheless, all has no longer long past correctly for Areva in executing the mission.

Areva is imagined to contain skilled serious manufacturing quality complications with the steam generator forgings in France. In stare of the claimed time criticality of the mission, to unravel these disorders Eskom and Areva agreed that the uncompleted forgings would be air-freighted to China where an Areva “associate” would full the make.

It sounds as if, every of the six steam generator forgings required the hiring of a Russian Antonov freighter plane (six flights in full) to flee the forgings from France to China. Nonetheless, in holding with an impeccable source, after taking a more in-depth stare on the forgings, Areva’s Chinese language associate made up our minds to scrap them and commence all over again from scratch.

One can easiest speculate as to why it became no longer understanding of less costly for Areva to flee engineers from the Chinese language manufacturer to France to stare the steam generator forgings, as in opposition to flying all six steam mills to China for the inspection, sooner than them being scrapped in China.

A historical senior nuclear govt at Eskom commented to this author on the time that: “This became the most costly transport of scrap metal in the historical past of humankind”.

Eskom has since confirmed to EE Trade Intelligence closing week that: “The forgings didn’t meet the expected quality requirements and can no longer be permitted, and due to the this truth they had been scrapped by the contractor at their non-public fee”.

In holding with Eskom, the contractual supply date of all six steam mills became February 2018, with the contractual completion date for the bogus of all six steam mills being the conclude of 2019.

Nonetheless, with the full delays in the mission, including restarting make of the steam mills from scratch in China, supply of the main three steam mills for Unit 1 at Koeberg is easiest starting now in September 2020, with those for Unit 2 easiest scheduled for supply in the third quarter of 2021.

Learn also:  Chris Yelland: Musical chairs at teach nuclear corporation – may possibly possibly furthermore honest calm axed Necsa CEO be re-hired?

Regarding the loyal substitute of the steam mills, Eskom now says that: “Installation is aligned with the outages scheduled for 2021 and 2022 respectively for the 2 Koeberg reactor models (Unit 1 and Unit 2)”. No mention is now made by Eskom of the criticality for completion in 2018 cited by Eskom on the time as the reason on the support of inserting a more costly contract with Areva.

Whereas no longer answering particular questions on the fee overruns bobbing up for the mission, Eskom insists that: “The estimated fee-to-completion for the mission is interior the distinctive funds permitted in 2014”. Needless to deliver, here’s no longer very helpful, since the distinctive funds permitted in 2014 is no longer disclosed, and can honest calm contain been tremendously better that the contract mark.

Nonetheless, it appears to be like lunge that Eskom has in level of truth paid a premium for the bogus by Areva of the steam mills at Koeberg on the premise of a claimed three-month shorter completion time, when in level of truth completion will seemingly be some three years longer.

It’s an primitive trick, but it clearly calm works.

  • Chris Yelland, managing director, EE Trade Intelligence. 

(Visited 7,362 occasions, 7,362 visits this day)

.